The permanent, public record of this development — every mandatory milestone, the date it was scheduled for, the date it was met, and when each entry was written into the record.
Project ID bece97d0-0de4-41f8-a600-372e2aea3f67
Reported delays
One milestone on this record is reported delayed. Scheduled dates are shown as they were published, beside the dates actually met.
Milestone by milestone
Met on the date it was scheduled for.
Site handed over, hoarding erected and the development registered with its permanent CoBuilt project ID. The construction programme was published on this date.
Entry 01 · recorded 4 Mar 2024 · 09:20 WAT
How this record is kept
15 days later than scheduled.
Piling and ground beams complete across all eight blocks. Dewatering through April extended the substructure programme; the published date stands as issued.
Attached to this entry
Entry 02 · recorded 2 Jul 2024 · 16:05 WAT
6 days ahead of schedule.
Frame and floor slabs topped out across the terrace, slab by slab. Recovered six days against the published date.
Attached to this entry
Entry 03 · recorded 5 Nov 2024 · 11:40 WAT
22 days later than scheduled.
The terrace is closed in. Roof covering and rainwater goods complete; a revised tile specification added three weeks to the published date.
Attached to this entry
Entry 04 · recorded 14 Mar 2025 · 14:15 WAT
MEP
Reported delayed. The scheduled date above stands as it was published, and has not been revised.
Mechanical, electrical and plumbing first fix. Reported delayed: the switchgear order is held at port. The scheduled date above has not been revised, and a new date will be published once the delivery is confirmed.
Attached to this entry
Entry 05 · recorded 1 Jul 2025 · 10:00 WAT · revised 12 Sep 2025 · 09:30 WAT
Internal and external finishes in progress, following the specification as built.
Entry 06 · recorded 15 Oct 2025 · 08:45 WAT
Works certified complete, with the snagging position stated in full.
Entry 07 · recorded 4 Mar 2024 · 09:20 WAT
Keys, documentation and warranties transferred to purchasers. The record stays open after handover.
Entry 08 · recorded 4 Mar 2024 · 09:20 WAT